Overview of Progress
Implementation of the Innovation Lab Process and 12 respective Process Lines in Bangladesh under the Innovations for Climate-smart Urban Development (INCLUDE) Project.
Project Background
The Innovations for Climate-smart Urban Development (INCLUDE) project, funded by BMZ and implemented with support from GIZ, promotes locally led climate-smart urban development in Bangladesh. The assignment supports four municipalities: Sirajganj, Gaibandha, Chapainawabganj, and Charghat. Through the Innovation Lab Process, the project helps selected local ideas move from concept refinement into practical implementation. The current assignment focuses on phases 5 and 6 of that process: refinement, development, validation, implementation, and integration of small-scale measures into municipal systems. Twelve innovation lines are being supported across themes such as urban heat resilience, water security, drainage, waste management, health risk reduction, climate-resilient agriculture, digital tools, and inclusive community engagement. The work also emphasizes participation of marginalized and climate-vulnerable groups, including women, youth, elderly people, and people with disabilities. Dorsch Impact and NIRAS support GIZ, LGED, municipalities, idea providers, developer teams, and local partners through coordination, technical inputs, capacity development, partnership building, knowledge management, procurement preparation, progress monitoring, and reporting. This dashboard consolidates project status, milestone progress, idea-wise implementation updates, quarterly progress summaries, deliverables, and expert input planning into one operational view.
Work package and milestone status
Milestone Status
Work Package-wise Progress
| Work Package | Total | Submitted | In Progress | Pending | Progress |
|---|---|---|---|---|---|
| WP1 Assignment Management and Coordination | 10 | 4 | 1 | 5 | 48% |
Milestone Register
Showing all milestones
| ID | Milestone | Delivery | Status | Progress | Remarks |
|---|---|---|---|---|---|
| 1.1 | Inception Report | End of month 3 | In progress | 75% | Submitted 31 January 2026 |
Innovation line updates by municipality
Showing all innovation lines
| Municipality | Idea | Status |
|---|---|---|
| Sirajganj | Urban heat resilience | Workbook-driven status summary |
Summarized narrative from Quarterly Progress Reports
QPR1 Summary
Jan-Mar 2026Completed Activities
- Mobilized lead experts, assignment management, communication/PR expert, and municipal coordinators.
- Conducted stakeholder consultation workshops in Sirajganj, Gaibandha, Chapainawabganj, and Charghat.
- Held bilateral meetings with idea providers to understand technical logic, readiness, costing, and governance.
- Established Microsoft Teams-based knowledge management systems for internal and GIZ collaboration.
- Prepared idea-specific stakeholder maps, preliminary site longlists, partnership scoping, and needs analysis.
Submitted Deliverables
- Inception Report package, including management, communication, process, third-party, engagement, and capacity concepts.
- Annual Planning Workshop Report for 2026.
Next Quarter Priorities
- Partnership development and initial partnership meetings.
- Needs analysis, design refinement, and idea-specific design workshops.
- Procurement support, survey requirements, technical specifications, and tendering documents.
Actual/current versus planned expert resources
Actual/current values are calculated through the current month.
Expert Detail
Showing all experts
| Code | Name / Designation | Group | Allocated | Actual/Current | Planned/Future | Balance |
|---|---|---|---|---|---|---|
| KE | Workbook-driven expert row | Lead | 0 | 0 | 0 | 0 |